Page tree

For an introduction to Advanced Scheduling, please visit the How to Understand Concepts within Advanced Scheduling page.

  1. Access the the Activity Scheduler for the desired Activity and click the Resource Usage button next to the event you want to access the resource usage for.

 2. The Resource Register tab for the selected event appears.



3. If desired, filter the list using the drop-down menus at the top of the Resource Register tab.

 If you want to see the resource usage for the whole Activity, select (All Events) from the Events drop-down.

Resource usage not registered by the system can be manually registered via the Add new resource usage button in the bottom left corner of the tab.

3. Click the backward arrow icon to return to the Activity Scheduler.

For further information, visit our Advanced Scheduling pages, and view our Activity Manager Training Videos.