Start and End dates are required to start working with your new Activity. The Activity will be running throughout the time range that the start and end dates determine.
The start and end dates fill in automatically after a new Activity is created:
by default, the start date is set to midnight of the day you created the Activity, and the end date is at 11:55 PM on the following day.

Manage the Start and End Dates:

  1. On the Basics tab of the Edit Activity pop-up, click on the calendar icon or anywhere in the Start date field →  a calendar pops up below.
  2. Select the month and year at the top.

(lightbulb) Move to the next or previous month with the arrows on the sides.

(lightbulb) With the Now option you can the select current date and time with one click.


3. Click on a date in the calendar to select a day.

The calendar only saves the date if a day is selected. Changing the year and month is not enough to save a new date.

4. Adjust the hours and minutes with the horizontal sliders at the bottom.
(info) The minute slider has 5-minute time-step intervals.

5. Repeat the above steps to set the End date.

(warning) The system does not allow you to pick an end date before the start date.